Why the levels exist
The finish level standard exists so that everyone — architect, general contractor, drywall contractor and painter — means the same thing by 'finished'. Without it, 'finished' is an argument waiting to happen at closeout.
Levels 0, 1 and 2
Level 0 is board hung with no taping, used for temporary construction. Level 1 has tape embedded in joint compound, typically in concealed plenum spaces. Level 2 adds a thin coat over tape and fasteners — suitable behind tile or in service areas such as garages and warehouses.
Level 3
One additional coat over tape and fasteners, with tool marks and ridges removed. Level 3 suits surfaces receiving heavy texture or heavy wall coverings. It is not appropriate under flat paint.
Level 4
Two separate coats over tape, three over fastener heads, sanded smooth. This is the workhorse specification for most commercial and residential interiors receiving flat paint or light texture.
Level 5
A skim coat of joint compound over the entire surface on top of Level 4. Level 5 is what you specify when gloss or semi-gloss paint, or severe critical lighting such as long window walls or wall washers, would otherwise reveal every joint and fastener.
The practical advice
Specify Level 5 where critical lighting or sheen genuinely demands it, and Level 4 nearly everywhere else. Over-specifying wastes labour; under-specifying produces a visible result nobody is happy with. If you are unsure, tell us the lighting and paint sheen and we will advise.